Last photos of 2014!
The most recent photos of our Redevelopment project; Phase 2; the housing project, were taken just before Christmas. (Thanks to Ron R. for these!)
December 22nd saw a major concrete pour which really changed the site. All of the concrete work for the Lower Parking level is completed, which includes the ceiling for that level which forms the floor for the Main Parking level. The ramp down from street level to the parking area has also been completed. Progress has been really good, thanks in no small part to the warmer weather that arrived with perfect timing for that major pour. See https://kamloopsunited.ca/photos/?album=Dec2014Phase2RedevelopmentUpdate